← Back to all calculators
Pipe Trench
Excavation, bedding, pipe displacement, backfill, and spoil truck loads.
Trench
Pipe & bedding
Quantities
Excavation177.78cy
Bedding11.11cy
Pipe displacement5.82cy
Initial backfill (sand/select)38.63cy
Common fill (above)122.22cy
Total backfill160.85cy
Spoil & hauling
Spoil (loose)213.33cy
Truck loads15.2loads
Spoil = full excavation as bank volume × (1 + swell). Reused common fill on site reduces hauling — confirm with project specs.